I created this table based on a lot of uploaded data from M-plates that can be found throughout the Internet. It shows the planned production data according to the m-plates of individual T2 buses (model year 1968, already built in 1967) – in other words, that’s the schedule showing how Volkswagen planned the serial production at the time. Interestingly, there is not a single Saturday or Sunday on all of these days, although there was also weekend work at VW at the time.

Source: M-Plate Decoder
Month: Day: Chassis Nr.: Notes:
JULY Th.,
13.07.1967
2X8
000 399
Planned day of build
according to M-Plate
Fr.,
14.07.1967
2X8
001 609
Planned day of build
according to M-Plate

VW FACTORY HOLIDAY: Mo., 17.07.1967 to Fr., 04.08.1967

AUGUST Mo.,
07.08.1967
2X8
001 769
Planned day of build
according to M-Plate
Th.,
31.08.1967
2X8
015 014
Planned day of build
according to M-Plate
SEPTEMBER Fr.,
01.09.1967
2X8
015 250
Planned day of build
according to M-Plate
Fr.,
29.09.1967
2X8
030 504
Planned day of build
according to M-Plate

PRODUCTION OF NEW BUILDS STOPPED FOR 1 WEEK?
No new planned DOB between Sa. 30.09.1967 and So., 8.10.1967

OCTOBER Mo.,
09.10.1967
2X8
030 535
Planned day of build
according to M-Plate
Tu.,
31.10.1967
2X8
042 143
Planned day of build
according to M-Plate
NOVEMBER We.,
01.11.1967
2X8
042 302
Planned day of build
according to M-Plate
Th.,
30.11.1967
2X8
059 185
Planned day of build
according to M-Plate
DECEMBER Fr.,
01.12.1967
2X8
059 432
Planned day of build
according to M-Plate
Fr.,
22.12.1967
2X8
072 378
Planned day of build
according to M-Plate
JANUARY 1968 Tu.,
02.01.1968
2X8
072 502
Planned day of build
according to M-Plate

In contrast to that, there is a table on TheSamba.com, which – in my opinion – shows the actual production numbers of the T2 buses for 1967. This makes it clear once again that not everything went according to plan in the early phase of T2 production. And it shows also that the numbers were sometimes well behind. Here is the table:
* (The only date that i added myself is July 10th, as this is also proven – the rest comes from TheSamba)

Source: TheSamba – List of Chassis Numbers
Month: Day: Chassis Nr.: Notes:
JULY * Mo.,
10.07.1967
2X8
000 038
Official DOB according to
VW birth certificate

VW FACTORY HOLIDAY: 17.07.1967 to 04.08.1967

AUGUST Th.,
31.08.1967
2X8
011 837
Acc. to TheSamba:
list of VIN numbers
SEPTEMBER Sa.,
30.09.1967
2X8
025 839
Acc. to TheSamba:
list of VIN numbers

PRODUCTION OF NEW BUILDS STOPPED FOR 1 WEEK?
No new planned DOB between Sa. 30.09.1967 and So., 8.10.1967

OCTOBER Tu.,
31.10.1967
2X8
042 257
Acc. to TheSamba:
list of VIN numbers
NOVEMBER Th.,
30.11.1967
2X8
060 116
Acc. to TheSamba:
list of VIN numbers
DECEMBER Su.,
31.12.1967
2X8
073 585
Acc. to TheSamba:
list of VIN numbers

A direct comparison of these two tables shows that:

  • 3,117 cars were behind schedule at the end of August,
  • and they were 4,665 buses late by the end of September.

It was not until October 1967 that VW managed to catch up with the schedule and continued with the T2 bus production as planned. This may be related to the one week (beginning of October) – completely without any new planned production days for buses.

By „no new planned production days“ i mean that i could not find a single bus in all m-plate databases (with more than 600 results for 1967 built 1968 VW T2 models), that has a planned DOB between Sa. 30.09.1967 and Su., 8.10.1967.

Maybe this week was used to just „catch up“. In other words, they might not have started to build any new buses that week, but instead just finished the projects that they already started.

Here are 3 examples of individual buses that also confirm the progress that was made until the end of October 1967:

Chassis Nr.: Planned Production date according to M-Plate: Actual Production date
according to birth certificate:
2X8
000 067
12.07.1967 17.08.1967
2X8
013 723
30.08.1967 11.09.1967
2X8
031 641
10.10.1967 13.10.1967

(Thanks again to the owners who allowed me to use their vehicle information for pointing this out)



*** Update: After reading my text, Wolfgang sent me those additional words:

„You are writing about the theory that either factory vacations were actually held at that time – or that production was stopped to rebuild the factory’s infrastructure for the production of the T2.

It is one and the same. VW has always – as far as I can remember – had factory holidays because you cannot keep production going when a large part of the workforce is on vacation. I checked it out: the plant should have had almost 25,000 employees in 1967 (1963: 22,000, 1970: 28,000). The vast majority of them were employed in production, which was shut down during the plant holidays. This was true not only in 1967, but in all years. During the factory holidays there was always rebuilding, due to production technology, quantity changes, iteration optimization, model changes etc. In 1967 it was a bit more work than usual, but it was nothing fundamentally different.

So only a few thousand people worked during the factory holidays. Of course there were also some from production, because during the holidays the parts inventory for the new model had to be increased so that everything was prepared at the start of production.

Car production in the sixties was completely different from what we know today. Today, all the necessary components are delivered and installed on the assembly lines just-in-time. It is a huge, highly networked system that can only be controlled with powerful computers.

At that time, parts production mainly consisted of individual machines or small streets, all of which were decoupled from one another by interim storage facilities. For example, a certain part was manufactured in the stamping one day, packed in wire mesh boxes and transported to the warehouse – and it was the same with another part the next day. And another one again a day later. Sometimes it was possible to punch an entire month’s supply within a few hours and other parts, such as the vehicle roofs, were usually delivered directly from the press line (“Dachstraße”) to the so-called shell.

And these interim storage facilities for the individual parts all had to be filled before production started. In other words, parts production ran at times without cars being built.

And that is why it is of course correct that T1 and T2 were partly built in parallel, at least in their individual parts and components. It may also be the case that one of the final assembly lines for the T2 was set up before the factory holidays started – in order to start it up during the holidays. But I don’t remember that anymore. In any case, it took several weeks after the holidays before all processes ran smoothly, everything else would have been a miracle. There was no simulation like today.

Even after the start-up of the T2, T1 parts and components were of course still produced in production, since the T1 spare parts came from the same production lines. 

Today, most of the individual components for the final assembly of a vehicle are manufactured individually, supplied at the right time and belong exactly to this vehicle. At that time, most of the components were made anonymously and were only assigned to the special car during final assembly. Otherwise it would not have been possible to control it with the means at that time.“


Get back to the topic overview.

Or continue reading through my research in chronological written order:

  1. The oldest T2 (baywindow) bus
  2. VW works vacation – summer 1967: vacation locks, remodeling of the assembly lines & delays
  3. Summer 1967: End of the splitbus era, start of earlybay production
  4. Production figures of the VW T2 for 1967    (=current site)
  5. VW T2 register and surviving 1967-built buses